Through the end of September, the Improve McHenry team reached another project milestone!

Construction crews completed the second concrete pour for the new western half of the McHenry Avenue bridge. A total of 96 trucks were required to deliver the extraordinary amount of 910 cubic yards of concrete to the project site. What’s more is that crews completed the pour in just one day!

The McHenry Avenue Corridor Improvements Project is now 65% complete! The project continues to progress on schedule and is anticipated to be completed in 2020.